SCPro will launch with an initial group of agencies July 1, 2025. Agencies included in the initial launch are non-inventory and non-plant maintenance agencies. These are referred to as Wave One agencies.
Agencies that use the inventory and plan maintenance functionality in SCEIS will go live with SCPro Oct. 6, 2025. These are referred to as Wave Two agencies.
The SCPro project timeline is:
-
Sept. 30, 2024-Feb. 28, 2025: System Integration Testing
-
April 7-May 23, 2025: User Acceptance Testing
-
May 5-30, 2025: Train-the-Trainer Training
-
June 2-30, 2025: Statewide End User Training
-
July 1, 2025: Wave One Go Live
-
Oct. 6, 2025: Wave Two Go Live
View the SCPro implementation timeline and full list of agencies in Wave One and Wave Two.
Wave Three will include higher education institutions and local governments.